Step 1: Open the Summary report
Go to Time > Reports and click Summary.
Step 2: Pick the period
Use the date field in the top-right, for example This Month or Last Month, or a Custom Range.
Step 3: Group by project
Under Group by, choose Project. The table lists each project with its client and total duration.
Step 4: Focus on one client or project
To see one client’s work, select it in the Client filter and click Filter. To see one project, select it in the Project filter. The Total time at the top updates to match.
Compare Against Estimates
To check hours against a project’s plan, open the project in Time > Projects and tasks. Its Time logged card shows the hours logged against the estimate.